Restoration of the only surviving
Baker 20-40 Steam Tractor
Assembly
Front
wheels back on, primed but not painted yet. The axle housing being installed. |
|
Axle installed, rear wheels going on. |
|
Back on all four again. |
|
Installing the front skid bands. |
|
Installing the differential. |
|
Differential installed. |
|
Installing one of the studs that were broken. |
|
Boiler ready for installation. |
|
Boiler Installed. |
|
Condenser assembled after radiator shop tested each tube
and resoldered the tubes on both ends. |
|
New lugs installed. |
|
Pouring a new valve guide |
|
Lawrence admiring the pour. |
|
Outer tubes of the super heated removed. The will be
replaced. The inner tubes are good. |
|
Nicholas guiding the engine proper into place |
|
Nicholas guiding the intermediate gear into place. |
|
Steering quadrant installed. |
|
Nicholas installing the pump rod. |
|
Eileen cutting shims out for the intermediate shaft
bearings. |
|
State of Minnesota boiler inspectors thickness testing the
rear flue sheet. After the thickness test passed for 300 lbs, a hyrdostatic test
to 375 lbs was performed. The boler passed for 300 lbs. This is what the engine was designed to run. |
|
Lawrence pouring filler between the boiler and cradle it
rests upon. |
|
Lawrence and Nicholas installing the clutch. |
|
Installing the fan pully drive wheel. |
|
Installing the flywheel. |
|
Installing the condenser. |
|
Current progress on June 12, 2015. 13 days before NTA
starts. |
|
Major items left include completing the superheater, the firebox
and piping. The restoration crew is optimistic it will be completed and
operational at NTA’s 2015 Baker feature. |
|